Construction Update - 2024-02-01
YourLand Developments

We are pleased to share monthly construction updates for Stage 1 for Society 1056

Titles for this stage are anticipated in Q1 of 2025.

 

November 2024: Construction Update 

– Civil works such as topsoiling and nature strips are forecast for completion this month. We are currently going through authority compliance testing and audits.

Stage 1 titles at Society 1056 are fast approaching!

—————–

Step 1: Valuation Access

– Valuers will have on site access to Stage 1 from Monday, 18 November 2024 by appointment only. Your financial institution or mortgage broker can request an appointment directly by contacting:

Nick Carter – Project Manager
Winslow Construction
Phone: 0460 303 085
Email: nickc@winslow.com.au

Important Access Information
– Access is for valuers only. No builders or purchasers will be permitted onsite. All valuers must wear appropriate Personal Protective Equipment (PPE) and show a valid WorkSafe accreditation upon entry.

October: Construction Update

– Sewer, drainage, and internal electrical works are now complete, with testing and compliance scheduled for the coming weeks.

– Footpaths and topsoiling are now in progress.

 

September 2024: Construction Update
– Sewer and water services complete.
– Electrical trenching and pavement works ongoing.

 

August 2024: Construction Update
– Sewer service construction is complete with drainage construction underway.

 

July 2024: Construction Update
– Construction of drainage services are underway.

 

June 2024: Construction Update

– Sewer service installation is now complete
– Preparations for drainage installation are underway

 

May 2024: Construction Update

– Sewer works are nearly complete.
– Preparations for roads and pavements are underway, with excavation works preparing these areas.

 

April 2024: Construction Update

– Construction continues with bulk earthworks advancing.
– We have initiated service trenching marked by the commencement of sewer pipe installation.

 

March 2024: Construction Update

– Stage 01 construction has commenced!
– Earthworks and trenching are underway in anticipation for essential services.

 

February 2024: Construction Update

– Construction is scheduled to commence in Q1 2024

 

 