STAGE UPDATE
STAGE 01 CONSTRUCTION UPDATES
YourLand Developments
We are pleased to share monthly construction updates for Stage 1 for Society 1056
Titles for this stage are anticipated in Q1 of 2025.
November 2024: Construction Update
– Civil works such as topsoiling and nature strips are forecast for completion this month. We are currently going through authority compliance testing and audits.
Stage 1 titles at Society 1056 are fast approaching!
—————–
Step 1: Valuation Access
– Valuers will have on site access to Stage 1 from Monday, 18 November 2024 by appointment only. Your financial institution or mortgage broker can request an appointment directly by contacting:
Nick Carter – Project Manager
Winslow Construction
Phone: 0460 303 085
Email: nickc@winslow.com.au
Important Access Information
– Access is for valuers only. No builders or purchasers will be permitted onsite. All valuers must wear appropriate Personal Protective Equipment (PPE) and show a valid WorkSafe accreditation upon entry.
October: Construction Update
– Sewer, drainage, and internal electrical works are now complete, with testing and compliance scheduled for the coming weeks.
– Footpaths and topsoiling are now in progress.
September 2024: Construction Update
– Sewer and water services complete.
– Electrical trenching and pavement works ongoing.
August 2024: Construction Update
– Sewer service construction is complete with drainage construction underway.
July 2024: Construction Update
– Construction of drainage services are underway.
June 2024: Construction Update
– Sewer service installation is now complete
– Preparations for drainage installation are underway
May 2024: Construction Update
– Sewer works are nearly complete.
– Preparations for roads and pavements are underway, with excavation works preparing these areas.
April 2024: Construction Update
– Construction continues with bulk earthworks advancing.
– We have initiated service trenching marked by the commencement of sewer pipe installation.
March 2024: Construction Update
– Stage 01 construction has commenced!
– Earthworks and trenching are underway in anticipation for essential services.
February 2024: Construction Update
– Construction is scheduled to commence in Q1 2024